Update on Cedar Brae fiber rebuild

CaptureRe the timeline on the south shore fiber rebuild: The successful bidder has until March 15 to submitted the required paperwork (bonding, insurance, etc). With that paperwork in hand, the PUD will issue the notice to proceed and the contractor has 92 days to finish the work. As to when the contractor will start mobilizing and get to work, it\’s up to them. They must submit a detailed schedule for the work, however the PUD doesn\’t set what gets done when as long as the work is finished to our satisfaction within the 92 days. Don’t know if the PUD crews will proceed with restoration of individual hook-ups before the entire cable is in place or not.